Interconnection approval
Interconnection approval is SDG&E's written Authorization Required to Operate before a generating facility operates in parallel with the distribution system under Electric Rule 21.
policy · Concept code GS-CONCEPT-182 · Last verified September 29, 2026
Evidence through 2023-08-29 · 0 sources have no source-event date
Content modified 2026-09-29
Definition and decision context
Why it matters
That tariff authorization is separate from City inspection and does not mean SDG&E has warranted a design, granted a generic construction approval, or made a permission-to-operate promise outside Rule 21.
Review confirmed · Review due October 29, 2026
The previous review deadline was September 27, 2026. The missed interval remains unverified; the current review does not establish historical coverage.
The cited evidence supports this statement within the source’s stated scope. Its jurisdiction and source-event date limit its applicability to a particular project.
Applicable jurisdiction: US-CA
Verified September 29, 2026
Definition
Interconnection approval is SDG&E's written Authorization Required to Operate before a generating facility operates in parallel with the distribution system under Electric Rule 21.
Review confirmed · Review due October 29, 2026
The previous review deadline was September 27, 2026. The missed interval remains unverified; the current review does not establish historical coverage.
The cited evidence supports this statement within the source’s stated scope. Its jurisdiction and source-event date limit its applicability to a particular project.
Applicable jurisdiction: US-CA
Verified September 29, 2026
Selector-derived public graph
Learning navigation
Primary topic: Policy
Broader topic
No public concepts recorded.
More specific topics
No public concepts recorded.
Related topics
No public concepts recorded.
Learn first
No public concepts recorded.
Builds toward
No public concepts recorded.
Primary sources
- San Diego Gas & Electric: SDG&E Electric Rule 21 § D.5; printed tariff Sheet 26; PDF page 25; Cal. P.U.C. Sheet No. 36517-E; Advice Letter 4032-E; effective 2023-08-29
Revision tariff Sheet26, Cal.PUC36517-E, AL4032-E, submitted2022-07-01, effective2023-08-29 · Source event as of August 29, 2023 · Ontology accessed September 29, 2026 · Ontology verified September 29, 2026
- San Diego Gas & Electric: SDG&E Electric Rule 21 § D.1 Authorization Required to Operate; printed tariff Sheet 25; PDF page 24; Cal. P.U.C. Sheet No. 36516-E; Advice Letter 4032-E; effective 2023-08-29
Revision tariff Sheet25, Cal.PUC36516-E, AL4032-E, submitted2022-07-01, effective2023-08-29 · Source event as of August 29, 2023 · Ontology accessed September 29, 2026 · Ontology verified September 29, 2026